The main partner of the Foundation, the construction company Intergal-Bud, has provided a premises where a medical base is currently being established.
- The medical center will be located in the park area of the Dniprovsky district of Kyiv.
- It will occupy 4 floors, including a basement floor, totaling 1,538.52 square meters
- Doctors' offices and diagnostic centers will be located on the first floor.
- On each of the three upper floors, there will be wards, procedure treatment rooms, and doctor's offices.
- One floor will accommodate 12-16 beds for patients. In other words, the medical center will be able to provide assistance to 44 patients simultaneously on an inpatient basis.
After the construction of the main rehabilitation center is completed, medical institutions will be relocated to Zakarpattia region while the consultative and diagnostic department in Kyiv will continue to function there.
The Kyiv Medical Center is scheduled for start-up in the first half of 2024.